Street Projects

The City of Richmond Heights works hard to keep it's infrastructure safe. See the list below of street projects in the City.

Check back regularly to see what's happening around town.

Street Projects

Dale Avenue - Missouri American Water Main Replacement Project
June 2022 Update:
  • The contractor has installed all of the new watermain along Dale between Hanley and Big Bend.
  • The service contractor has transferred 80% of water services and should be completed with service transfers by the end of July.
  • We anticipate roadway and yard restoration to be completed by end of September.

January 2022 Update:
  • The water main on Dale Avenue will be replaced between Hanley Road and Big Bend
    • JH Berra has been awarded project and will start January 10th
    • Residents have been sent letters along Dale and received robocalls from MOAW
    • JH Berra replaced water main on Dale (east of Big Bend) and Big Bend in 2019 and has performed good work in the past within Richmond Heights
    • JH Berra will be starting the week of January 10th at the Hampton Branch Creek crossing and move towards Hanley Road in the east bound lane.
    • Soon after crews will begin heading east from Hampton Branch Creek in the eastbound lane.
  • Per contract, all water main shall be in the ground by end of April and all service transfers and pavement restoration shall be completed by end of July, weather dependent. 
Del Norte and La Veta Avenue - Missouri American Water Main Replacement Project
June 2022 Update:
June 29:
Work is expected to begin Tuesday, July 5 on Del Norte Avenue at Williams Avenue, working towards La Veta Avenue. Periodically, during the day (7am to 3pm), Del Norte may be closed to local traffic only to allow the contractor more working room to expedite their work.  Please follow detour signs when in place.
----- 
June 22: The contractor for Missouri American Water (MOAW) for the Del Norte and La Veta project is estimating a June 27 start date. This is dependent on when they can get their pipe delivered so will have a more definite answer soon. 
MOAW has sent letters and automated phone calls to residents along the route.

April 2022 Update:

MOAW has hired ECM Construction to replace the watermain and services on Del Norte and La Veta Avenue.  The watermain on Del Norte will be replaced between Bruno Avenue and La Veta Avenue and the watermain on La Veta will be replaced between Bellevue Avenue and Del Norte Avenue.  

Construction is scheduled to start the first week in June after schools are out for the summer.  The watermain should be installed in the ground within 8 weeks with service work to immediately follow.  

ECM will be responsible for all roadway restoration work on La Veta. ECM will only be installing a temporary asphalt patch on Del Norte as the City has a planned project starting in the spring of 2023 to reconstruct the street, sidewalk and driveway approaches.

ECM is scheduled to complete their portion of the project, including road restorations by the end of November.