2018 Concrete Slab Pavement Program


Please click here to view an overview of the 2018 Concrete Slab Pavement Program

The 2018 Concrete Slab Project consists of slab, sidewalk, driveway approach and ADA removal and replacement on portions of Lovella Avenue, Moorlands Avenue, and Mitchell Avenue.

The anticipated timeline for construction is between April 1st and June 30th, 2018.

For more information, contact Public Works Director Chris Boyd at cboyd@richmondheights.org or
at 314-655-3670.

Friday, June 15th
Update:

Sweetens Concrete has poured all of the pavement on Mitchell, Lovella and has a couple slabs to pour on Moorlands.  Sweetens still has to go through all of the streets to complete a few punchlist items including touch up on backfill behind curb.  All work should be completed by end of June per contract terms.


Thursday, April 12 Update:

Sweetens Concrete has been selected to perform project and has started to remove the north half of Mitchell including driveway approaches.  Once the north half of the street has been poured back and while they are waiting on cure time, they will move to Moorlands and Lovella to start removing and replacing half of the street at a time.  The contractor will hand out notices a couple days prior to removing your side of the street to let you know when you will need to be out of your driveway for a couple weeks.


Monday, February 5th Update:

More information to follow soon.